Lockheed F-35 Overruns Top $1 Billion, Government Auditor Finds
By Tony Capaccio - Mar 20, 2012 8:00 PM GMT+0100
Lockheed Martin Corp. (LMT)’s first 63 F-35 fighter jets are exceeding their combined target cost by $1 billion, showing the Pentagon’s costliest program lacks a reliable design and efficient manufacturing, according to U.S. congressional auditors.
The Pentagon is absorbing $672 million and Lockheed Martin the remaining $328 million in added costs for the aircraft in the first four production contracts, the Government Accountability Office said in prepared testimony today for a House Armed Services Committee hearing on tactical aviation. The committee is conducting the first oversight hearing on the F-35 Joint Strike Fighter for the fiscal 2013 budget.
The Pentagon is absorbing $672 million and Lockheed Martin the remaining $328 million in added costs for the aircraft in the first four production contracts, the Government Accountability Office said in prepared testimony today for a House Armed Services Committee hearing on tactical aviation. The committee is conducting the first oversight hearing on the F-35 Joint Strike Fighter for the fiscal 2013 budget.
“The long-stated intent that the Joint Strike Fighter would deliver an affordable, highly common fifth-generation aircraft that could be acquired in large numbers could be in question,” Michael Sullivan, the GAO’s director of acquisition management, said in the statement.
Ingen kommentarer:
Legg inn en kommentar
Merk: Bare medlemmer av denne bloggen kan legge inn en kommentar.