Boeing pushes back T-7 plans due to faulty parts
Feb 5, 03:15 PM
Boeing said Friday that quality problems with
parts slated for the T-7A Red Hawk training jet mean it
will delay by several months delivering the next test aircraft to the Air
Force.
Boeing is also now planning to start low-rate
initial production on the T-7 in mid-2024, several
months later than the company’s original plan. Boeing vice president and T-7
program manager Evelyn Moore told Defense News Friday that supply chain issues
were also why the company will postpone the planned start for its production
schedule.
Boeing’s
contract with the Air Force requires it to deliver the fourth and fifth
engineering and manufacturing development jets in December 2023 and January
2024, Moore said.
However, Moore said, the parts problem now means
the fourth jet will probably be delivered later this month, and the fifth jet
around March or April.
“We’ve struggled with some part challenges that
have caused delays” on those two jets, Moore said. “We’re really focusing on
safety and quality, and we are trying to get those jets delivered in the near
term.”
The Air Force plans to buy
351 T-7s from Boeing by 2034 to replace its fleet of aging T-38
jet trainers. The T-7 is designed to emulate fifth-generation fighters like the
F-35 and make it easier for the service to train new pilots to fly fighters and
bombers. The Air Force awarded Boeing a $9.2 billion contract in 2018 to build
the T-7 fleet as well as provide simulators and provide other support.
The Air Force told Defense News it did not
immediately have a comment on the T-7 delays.
Moore would not detail the type of parts that had
problems, but said they were multiple parts of varying sizes from several
different suppliers. Boeing had to send some parts back to their original
manufacturer for repairs, she said, and already suppliers have started quickly
fixing the faulty parts.
The fourth jet now has all of its necessary parts
installed, Moore said, and Boeing expects the “handful” of remaining fixed
parts for the fifth jet to arrive over the next few weeks.
Moore said Boeing has a quality team working with
its suppliers to understand what went wrong with the parts and address the
problems.
Boeing is now assembling the new T-7 production
line at its St. Louis facility, she added, and expects that to be done by
mid-2024. Shortly after that production line is ready, she said, Boeing plans
to start assembling LRIP T-7s.
A Government Accountability Office report in May
2023 said Boeing planned to start assembling its first production T-7 in early
2024.
Moore said Boeing could be ready to deliver the
first production T-7 in 2025, though she said there is a chance it could be
2026.
Boeing is required to start delivering T-7s 10
months after the Air Force issues an LRIP award, which could come in February
2025. Moore said that by starting production before the LRIP award, the company
could deliver jets before its 10-month deadline.
The Air Force expects to make a Milestone C
decision on whether to produce the T-7 in February 2025, and for deliveries to
start in December 2025. That planned production decision timeline is about two
years later than the Air Force originally intended.
GAO raised concerns in its 2023 report about
potential increased risk from having the T-7′s development, testing and
production phases overlapping. The auditing agency warned this approach can
lead to rising costs or schedule delays if problems are found in testing that
then must be fixed on the production line.
Moore acknowledged concurrency can be a danger,
but noted T-7s have carried out more than 500 flights so far and is about 60%
finished with its flight testing process, reducing the risk of overlapping
development and production.
“We’ve been flying the T-7 for several years,
collecting data [and] integrating that data into new software releases,” Moore
said. “It is a risk, but we are managing and mitigating that risk.”
Moore said Defense Contract Management Agency
officials are already conducting oversight inspections on components slated for
production T-7s.
Boeing delivered the first three of five planned
engineering and manufacturing development jets to the Air Force in 2023. One is
now undergoing flight testing at Edwards Air Force Base in California; another
is expected to wrap up climate testing at Eglin Air Force Base in Florida this
month. Boeing delivered the third aircraft in December, and it’s expected to
fly to Edwards this month.
The fourth and fifth test jets now in the final
phases of construction will stay at Boeing’s facility in St. Louis, Missouri,
Moore said, and will be used to check how well maintenance procedures match the
instructions laid out in the jet’s technical manuals.
Ingen kommentarer:
Legg inn en kommentar
Merk: Bare medlemmer av denne bloggen kan legge inn en kommentar.