Timeline: Events in Boeing's 737
MAX Crisis
(Reuters) - U.S. aviation authorities are poised as
early as Wednesday to lift a grounding order
(https://www.reuters.com/article/idUSKBN27Q00H) on Boeing Co's 737 MAX, a
long-delayed major step in a crisis caused by fatal crashes in Ethiopia and
Indonesia just five months apart in 2018 and 2019.
The
disasters killed 346 people, slashed Boeing's profit, prompted lawsuits and
investigations, including an active criminal probe by the U.S. Department of
Justice.
Here is
a timeline of events surrounding the 737 MAX:
2017
MARCH 8
- The 737 MAX gains U.S. Federal Aviation Administration (FAA)
certification.
MAY 22
- The 737 MAX enters commercial service on Lion Air subsidiary Malindo
Air.
2018
OCT. 29
- A Lion Air 737 MAX plane crashes in Indonesia, killing all 189 people on
board.
NOV. 13
- FAA, Boeing say they are evaluating the need for software or design changes to
737 MAX jets following the Lion Air crash.
NOV. 30
- Boeing weighs plans for a software upgrade for its 737 MAX in six to eight
weeks that would help address a scenario faced by crew of Indonesia's Lion
Air.
2019
MARCH
10 - An Ethiopian Airlines 737 MAX crashes, killing all 157 people on
board.
MARCH
12 - FAA says will mandate that Boeing implement design changes on the 737 MAX
by April that have been in the works for months.
MARCH
13 - FAA joins other major global regulators in grounding the 737 MAX, citing
evidence of similarities between the two fatal crashes.
APRIL 3
- The FAA says it is forming an international team to review the safety of the
now-grounded 737 MAX that will be headed by a formal top U.S. safety
official.
APRIL 6
- Boeing says it will cut monthly 737 MAX production by nearly 20%; U.S. and
airline officials say they believe the plane could be grounded for at least two
months.
APRIL
24 - Boeing abandons its 2019 financial outlook, halts share buybacks and says
lowered production due to the 737 MAX grounding has cost it at least $1 billion
so far.
MAY 5 -
Boeing did not tell U.S. regulators for more than a year that it inadvertently
made an alarm alerting pilots to a mismatch of flight data optional on the 737
MAX, instead of standard as on earlier 737s.
JUNE 17
- Boeing executives take turns apologizing for the loss of life in two 737 MAX
crashes and pledge to apply lessons of the crisis to future planes.
JULY 24
- Boeing posts its largest-ever quarterly loss due to the spiraling cost of
resolving issues with its 737 MAX.
SEPT.
25 - Boeing's board of directors creates a new permanent safety committee to
oversee development, manufacturing and operation of its aircraft and
services.
OCT. 22
- Boeing fires Kevin McAllister, the top executive of its commercial airplanes
division, marking the first high-level departure since the two fatal
crashes.
DEC. 12
- Boeing abandons its goal of winning regulatory approval for the 737 MAX to
resume flying in December after the FAA said the plane would not be cleared to
fly before 2020.
DEC. 16
- Boeing says it will suspend 737 production in January, its biggest
assembly-line halt in more than 20 years, as fallout from two fatal crashes of
the now-grounded aircraft drags on.
DEC. 23
- Boeing fires Chief Executive Dennis Muilenburg following a year of intense
scrutiny and industrial setbacks set off by twin fatal crashes of the 737
MAX.
2020
MARCH 9
- Ethiopian investigators single out faulty systems on a 737 MAX plane in an
interim report on the 2019 Ethiopian Airlines crash, piling pressure on the U.S.
jetmaker on the eve of the disaster's anniversary.
MARCH
11 - Boeing is freezing new hiring and overtime except in certain critical areas
to preserve cash, as the coronavirus outbreak compounds the MAX
fallout.
-
Boeing plans to separate 737 MAX wiring bundles, flagged by regulators as
potentially dangerous, before the jet returns to service.
MAY 27
- Boeing says it has resumed 737 MAX production at a "low rate", after halting
production in January.
JUNE 16
- U.S. senators introduce legislation to strengthen FAA oversight of aircraft
certification.
JUNE 17
- FAA chief Steve Dickson acknowledged Boeing and the U.S. air safety agency
both made mistakes on the 737 MAX.
JUNE 29
- Boeing begins a series of long-delayed flight tests of its redesigned 737 MAX
with regulators at the controls.
JULY 7
- Boeing has reached settlement agreements in more than 90% of the wrongful
death claims filed in federal court after the 2018 Lion Air 737 MAX crash in
Indonesia that killed all 189 people on board.
SEPT.
16 - An 18-month investigation by a U.S. House of Representatives panel finds
Boeing failed in its design and development of the MAX as well as its
transparency with the FAA, and that the FAA failed in its oversight and
certification.
SEPT.
28 - The leaders of the U.S. House Committee on Transportation and
Infrastructure introduce bipartisan legislation to reform the FAA's aircraft
certification process.
SEPT.
30 - FAA Chief Steve Dickson conducts a nearly two-hour evaluation flight at the
controls of a Boeing 737 MAX.
OCT. 6
- The FAA issues a draft report on revised training procedures for the 737
MAX.
OCT. 18
- American Airlines Group says it plans to return 737 MAX jets to service for
passenger flights by the end of this year.
NOV. 9
- The FAA says it is in the final stages of reviewing proposed changes to the
737 MAX, with sources telling Reuters the FAA was set to lift its grounding
order as early as Nov. 18.